Road Infrastructure Up gradation
The total sanctioned cost of this component is of Rs.8.04crores and the revised one is of Rs.2.50crore. In this regard Road Drainage & other site development works worth Rs.2.50crores have been completed.
Administrative Complex
The total sanctioned cost of this component is of Rs.3.65crores. The Administrative Complex has been completed. Total Rs.96.00lacs have been incurred towards the construction of this building.